Here's EXACTLY what's going on two years to the day builder of illegal Kettering flats should have demolished the lot

Two years ago today, a block of illegal Kettering flats should have razed to the ground, but as of February 28, 2026, the apartments remain defiantly standing in the town centre’s Job's Yard.

In November 2023, a High Court judge ordered Marcus Fielding, sole director, sole employee and brains behind the six-storey flats to demolish the planning permission-breaking building setting a deadline of February 28, 2024.

Defying the order for a staggering 731 days, North Northants Council (NNC) as local planning enforcers will once again return to the courts to seek his removal as Mr Fielding has refused to leave.

placeholder image
Read More
Demolition of illegal Kettering flats closer as police enable access to condemne...
Marcus Fielding builder of a block of flats in Job's Yard in Kettering/ National Worldplaceholder image
Marcus Fielding builder of a block of flats in Job's Yard in Kettering/ National World

In March 2025, NNC had successfully applied to the High Court for the rights to access the Job’s Yard site for the ‘purposes of carrying out the demolition and associated works’. Mr Fielding had also been ordered not to obstruct the work in any way.

Following a successful application to Northampton Magistrates Court, the council was granted a warrant to enter the Job’s Yard site under Section 95 of the Building Act 1984.

A spokesman for NNC said: “The council wrote to Mr Fielding several times in September and October 2025 informing him that we need him to vacate the newly built block of flats and adjacent land at Job’s Yard, so we can start proprietary works on its demolition and have provided him with contact details of support services he may require including Citizen's Advice, community law service and North Northamptonshire Council Housing options.

A block of flats in Job's Yard in Kettering/ National Worldplaceholder image
A block of flats in Job's Yard in Kettering/ National World

"We then attended site on October 22, 2025 with our demolition contractors, to commence the demolition works.

“Mr Fielding refused to vacate the property in advance of us attending the site, so the council following further legal advice are now making a revised application back to the courts to enable us to seek his removal.

“Once the site is secured it will become an active demolition site so it will be unsafe for Mr Fielding to return and enter the site without prior agreement with the council and the demolition contractor.”

In separate proceedings, Mr Fielding will appear at Northampton Magistrates Court in June over three charges brought against him and his company by the Health and Safety Executive (HSE) under health and safety legislation relating to the flats off Meeting Lane.