Possible five-year delay as work on £40m new Kettering maternity unit extension 'paused' as costs rise

Work on a £40m new maternity unit extension planned for Kettering General Hospital’s Rockingham Wing has been 'paused'.

The top floor of the Rockingham Wing remains closed off due to the presence of structurally unsafe RAAC (reinforced autoclaved aerated concrete).

A new £40m extension which was due to be added onto the maternity department had been planned to open in winter 2027.

Hospital chiefs have confirmed they are considering two options – finding more funding for the extension or go for a total rebuild that could cost £200-350m.

Maternity unit Rockingham Wing, Kettering General Hospital /IMGplaceholder image
Maternity unit Rockingham Wing, Kettering General Hospital /IMG

The University Hospitals of Northamptonshire (UHN) Group that manages Kettering General Hospital said it remains committed to providing high-quality maternity and neonatal facilities for the community.

A UHN spokesman said: “As part of our ongoing planning for future services, we have paused works beginning on the Rockingham Wing extension while we review the best way to deliver long-term improvements to our maternity, gynaecology and neonatal services.

“The recently received projected costs for the planned scheme are now expected to exceed the funding available to us from the NHS, with delivery timescales also extending beyond those originally projected.

"We have therefore taken the decision to pause while we explore our options and identify the most sustainable long-term solution for patients, families and our colleagues.”

UHN is currently considering two principal options through the NHS business case process – the previously planned Rockingham Wing extension and an alternative, new-build option.

The spokesman said: “The latter has become possible as a result of wider redevelopment at KGH, including the completion of our energy centre programme towards the end of next year, which will make land in the Car Park D area available for future development.

"The area is currently occupied by contractor compounds and temporary facilities supporting the energy centre works rather than being used for public parking.

“A new-build facility could offer a number of advantages, including the opportunity to create purpose-designed maternity, gynaecology and neonatal environments that better meet the needs of patients, families and our colleagues, while providing greater flexibility for future service developments.

"It also has the potential to deliver modern facilities more quickly than was previously anticipated through the extension and rebuild scheme. However, no decision has yet been made on a preferred option.

“At this stage, it is too early to provide confirmed costs, as proposals are still being developed and assessed through the required approval process.

"We expect the options appraisal and business case process to continue over the coming months, with a preferred option being identified once this work has been completed and the necessary approvals secured.

“Subject to the outcome of that process and the necessary approvals, our current planning assumption is that new-build construction could begin in 2029 and be completed approximately three years later, in 2032.”

The trust says staff, patients, families and other stakeholders will continue to play an important role in helping to shape future plans as this work progresses.

UHN’s spokesman added: “While we determine the best long-term solution, we will continue to invest in and improve our existing facilities where possible to support patients, families and staff.

“We recognise the significant work already undertaken to develop the Rockingham Wing extension scheme and thank everyone who has contributed so far. This work will help inform any future solution.”