Kettering Library roof scaffolding takes shape as contractors begin £6.8m budget repair

Contractors have begun the £6.8m-budget work to repair the roof of Kettering Library and Art Gallery.

Scaffolding is taking shape around the Grade II-listed complex for the project expected to take until the first week of August 2026.

A timeline published by North Northants Council has estimated scaffolding erection work will take just under four months.

Hide Ad
Hide Ad

The roof of Kettering Library will then be stripped and replaced starting in mid-August. The Alfred East Art Gallery will have its roof stripped and replaced starting at the end of September.

Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National WorldCornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World
Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World
Read More
Finish date for £6.8m-budget Kettering Cornerstone roof replacement project anno...

Re-roofing with a mixture of coverings, including a bespoke order of Collyweston stone, will take up to 10 months – scaffolding will remain in place until June 2026.

North Northants Council appointed contractor Messenger in February who will place a temporary roof over the building to enable work.

The Cornerstone complex comprising Kettering Library and the Alfred East Art Gallery needs major repairs to its roofs that became apparent after the addition of a £4.5m extension.

Hide Ad
Hide Ad
Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National WorldCornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World
Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World

The library remains temporarily relocated in the extension of Cornerstone for the ‘foreseeable future’.

- Start date: April 14, 2025

- Scaffolding erection to commence: April 28, 2025

- Start of library roof strip and replace: August 11, 2025

Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National WorldCornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World
Cornerstone - Kettering Library and Alfred East Art Gallery, work starts on roof repairs/National World

- Start of art gallery roof strip and replace: September 25, 2025

- Removal of scaffolding: June 6, 2026

- Project complete: August 5, 2026

Comment Guidelines

National World encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

News you can trust since 1897
Follow us
©National World Publishing Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice