Court hears of 'booby trapped scaffolding' at trial of planning permission-breaking Kettering six-storey apartment builder

Marcus Fielding, the builder of a planning permission-breaking Kettering six-storey apartment block has blamed ‘booby trapped scaffolding’ at a trial in Northampton Magistrates Court yesterday (Monday, June 22).

Mr Fielding, sole director and employee of company Michigan Construction Ltd, represented himself at court yesterday (Monday, June 22) in a case brought by the Health and Safety Executive (HSE) regarding a block of flats in Job’s Yard.

It was Mr Fielding’s fourth time in front of District Judge Amar Mehta, and once again Mr Fielding confirmed his not guilty plea to three charges – that he and his company failed to take steps to prevent danger to the public through the potential collapse of an unstable building and a potential structural collapse, and that he contravened a requirement imposed by a prohibition notice that forced him to take steps to ensure scaffolding was safe and it was prevented from collapsing.

placeholder image
Read More
Builder of illegal Kettering flats is 'sticking his middle finger up to the auth...
Marcus Fielding (centre) leaving Northampton Magistrates' Court where he has been charged under health and safety law relating to a block of flats in Job's Yard, Kettering/IMGplaceholder image
Marcus Fielding (centre) leaving Northampton Magistrates' Court where he has been charged under health and safety law relating to a block of flats in Job's Yard, Kettering/IMG

Three mirror charges have also been laid against the 53-year-old company director’s firm, Michigan Construction Ltd.

Mr Fielding told the court that he couldn’t afford legal representation so he was guided through the 1,837-page bundle by Judge Mehta and prosecutor for the HSE Tom Daniel.

The bundle contains a crucial report written by an independent structural engineer used in the High Court trial in November 2023, which ended with Mr Fielding being ordered to demolish the building.

Referring to himself and his company as ‘we’, he said: “We still dispute the validity of the report. We think it’s inaccurate.”

File picture of Job's Yard, Kettering, cordoned off/IMGplaceholder image
File picture of Job's Yard, Kettering, cordoned off/IMG

Mr Fielding said that he gained permission from the High Court in Birmingham to carry out ‘limited and remedial works’ to the building.

He said: “We have just kept the building safe and secure.”

Speaking of the ‘2,000 tonne’ building he built nearly single-handedly, Mr Fielding said there had not been any accidents or injuries, that he had a ‘high regard for health and safety’ and he had been carrying on with ‘remedial works’ over the past three years.

When asked by Judge Mehta if he was an authorised builder, Mr Fielding replied that he was a ‘competent builder’ and that he was the ‘expert’ on the building.

Job's Yard, Kettering in 2021/IMGplaceholder image
Job's Yard, Kettering in 2021/IMG

The Judge added: “It’s a 2,000 tonne building, not DIY.”

To show the extent of the breaches by Mr Fielding of the prohibition orders, videos taken by members of the public, residents and officials monitoring the site were played to the court showing Mr Fielding working on the scaffolding.

Witnesses said they had seen Mr Fielding working on the parapets, handling pieces of timber and putting furniture into the condemned building.

The court heard Patrick Kennedy of Reach Scaffolding, – a trained scaffolder – describe how he had supplied and fitted the scaffolding for the project. He visited every week to carry out safety checks until June 2022, when a prohibition notice was placed on Job’s Yard and work stopped. He was alerted by neighbours that Mr Fielding had been seen adjusting the scaffolding.

He said: “I went to the site to have a look. This fella (pointing to Mr Fielding) was taking it down.”

Mr Kennedy explained he lost about £64,000 on the job for Mr Fielding’s project.

After a brief apology, Mr Fielding cross-examined Mr Kennedy being reminded by the judge to ask questions.

He said: “Some of the scaffolding was booby trapped. It was filled with sand. Was it booby trapped?”

"No,” said Mr Kennedy, adding, “the scaffolding ties were taken out by this fella. He took them out to put in the windows.”

During evidence given by HSE construction expert Richard Humphries, a video played to the court showed a man – Mr Fielding – sat on a scaffolding plank, legs dangling down as he angle-grinded a scaffolding pole underneath him until it fell to the floor.

Commenting on the footage, Mr Humphries described the clip saying: “It’s very unsafe. There’s lots going on there.” Searching for the right words, he added: “If he’s cutting scaffolding poles whilst he’s up there, he’s not safe at all.”

Multiple witnesses said who they had been concerned about the state of the building, noise from the site and issues with access.

A local cub leader said she was ‘terrified’ that the building could collapse onto a nearby hall where children met.

The court heard HSE Inspector Mark Welsh had visited Job’s Yard in June 2022, serving a prohibition order to Mr Fielding, ordering him to stop work. He was warned several times that failure to comply was a criminal offence. He was asked for a plan as how to rectify the ‘issues’.

Mr Fielding was told repeatedly to send them his plan, but he failed to do so.

When asked by Judge Mehta if in Mr Welsh’s his expert opinion the Job’s Yard apartment block was safe, he said ‘no’.

Commenting on the email to Mr Welsh in which the builder described himself as ‘the expert’ on the site, Mr Fielding said it meant he was the expert because he’d been there ‘99 per cent of the days’ and knew every part of the building.

The High Court Case in November 2023, when a High Court judge ordered the Job’s Yard flats to be demolished, an order that should have been carried out by February 28, 2024.

Judge Mehta encouraged Mr Fielding to read the expert report by structural engineer David Smith of David Smith Associates, ahead of proceedings for day two of the hearing, adding that everybody else had.

The case continues.

Charges brought by the Health and Safety Executive are:

- that during the construction of the block he failed to take steps to prevent danger to the public through the potential collapse of an unstable building.

- that between June 2022 and April 2025 he failed to take practicable steps to prevent danger to the public from structural collapse.

- that between June 2022 and April 2025 he contravened a requirement imposed by a prohibition notice that forced him to take steps to ensure scaffolding was safe and it was prevented from collapsing.

Three mirror charges were laid against his company, Michigan Construction.

The building remains cordoned off.